daily log

Just left the site. Framers are done with all walls interior and exterior from the mech. room to the master bedroom. That area is ready for Roof CLT install early next week. Base connection steel is already installed in the kitchen area. The framers plan to install 4 more panels in the kitchen area today. We will start Roof panels on Monday/Tuesday next week. It will be nice to get the house and interior slab dried in and protected.