Daily Log

Back after the holiday break. Site looks good. Radiant floor heater still holding at 70ºF+ floor temp around 40ºF. Installed CLT’s are showing some sun darkening but nothing that can’t be sanded. No warping, cupping, or checking with installed CLT’s.

Job will be idle on site till Monday the 7th. As the framers can not make it this week. A full crew will be on site Monday.

The rest of the steel package is fabricated. Fabricators are finishing drilling holes and premiering the steel.