Framers installed the two big steel beams today along with two more roof panels. The roof panels are in the worst possible order from Smartlam for install. Given their size and weight it is extremely hard to move them around and time consuming to organize them according to where they need to be installed. The framers have spent most of their time this week doing just that. They plan to have all the roof panels on except the garage by Friday the 25th next week. They will stand garage walls and the garage roof the following week.

I have received most of our bids back. I will be putting all of that costing together to update the budget and get the subs under contract next week.