daily log

After letting the concrete cure for 11 days We removed the concrete tenting this morning. Becon engineering came out and laid out the CLT install grid line points. The framers and I snapped out the grid after. The concrete sub and I installed a house wrap to cover the concrete floors for protection. We will use concrete blankets over this to keep the slab warm over the next few months while we install the CLT’s