I have transferred the past Stillwater budget information over to the new Operating Budget. I will begin to fill in and change our current numbers next week with the following:

  • Savings I think we have/can make.

  • Real costs based on contracted subcontractor bids

  • Bid information / changes already made but not reflected in Stillwater Budget. [ie. SmartLam org. bid $90k Real already paid costs are higher. ]

  • Added scopes that were missed in budgeting exercise with SW. [ie. CLT Rigging]