Daily log

Framers are done till after insulation. At that point they will return and sheet the house with OSB.

Daily Log

Sanders are in the game room and Allen’s bed room. Framers are installing the tension rods in the garage. Radiant and HVAC teams are on site installing thermostat wire, coolant lines, and ductless heads.

Daily Log

Framers are finishing up today. They will return Monday and Tuesday next week to clean up and install the Tension Rods in the Garage. Bend Heating is on site installing coolant lines for the ductless heads. The framers have framed mechanical chases for everyone to run their lines in on the roof.

daily log

Finish crew started sanding Tuesday the 12th. They are getting their feet under them using the new sanders. But they are moving fast. They are already in the master bath and almost done. They will work around the house counter clockwise starting at the master.

daily log

Framers have the garage roof and the Great room roofs left. Will be done with the garage today and started on the great room. Still dealing with snow and ice in the shaded areas like the courtyard and the north side of the home.

Daily log

We have removed the majority of the snow to continue working. The schedule has lost roughly 2 weeks due to it. Today the framers are back and framing the exterior again. We are about 70% done. Tension rod hard ware has been delivered to the site.

Daily log

The last 3 days have brought about 3’ of snow. It has stopped work on site completely. Today is the first clear day. We have started snow removal.

daily log

Framers finished exterior wall over framing. I cleared ice and snow off the roof metal areas and set all the steel with the framers.

daily log

Framers called it an early day today because of weather. I spent the day dialing in the sanding technique for interior sanding. Sanding went good. It should take about 2.5-3 weeks to sand the entire house. Similar to the time frame of a drywall crew drywalling the entire house. Framers plan to finish the exterior wall over frame tomorrow and set roof steel in preparation for roof over frame. I have updated all the next trades with our current schedule and they are all good to go once ext. Framing is done.

Daily Log

Framers are finished with Interior wall framing. They have also finished scraping and hold downs on the exterior of the CLT’s and begun exterior over frame.

Daily log

Framers are plunging along with interior walls and attic spaces.

daily log

Snowing today pretty good. Framers finished CLT Set on Friday and started installing hold downs and structural screws on the CLT’s . They are moving to interior framing since it’s snowing.

daily log

Framers finished CLT Set yesterday. Friday the 1st. I spent today covering the rest of the openings with reinforced plastic and cleaning. We will be ready for ext. wall over frame on Monday. Family came by to see the house.

Daily log

Framers set the big gable end panel on the garage today along with the 4 roof panels on the western face of the garage. Should be able to finish up by tomorrow.

Daily Log

Framers are setting the last Interior wall. The last wall was sent from Smartlam extra long so that we could cut on site to account for garage slope. The last wall fit perfectly. We had zero major issues with the walls. Radiant team finished the Snow melt in the courtyard.

Daily Log

Framers are setting the last of the interior walls today and tomorrow in the garage area. Last of the roof panels will begin Wednesday. Radiant team started the snowmelt install in the courtyard. Building solution delivered all of the over frame materials to the site. I got the entire interior of the house clean. It’s really starting to take shape.

Daily log

Covered 90% of the openings on the building. Hopefully this holds in some heat. Plan to do a big clean inside and out Monday.

daily log

Farmers are finishing up the last two panels over bathrooms 112 & 115 this afternoon. Should be ready for me to cover the openings this weekend.

daily Log

Framers were back on today. Setting roof panels over the game room and baths 112 & 115. Should be done with this section tomorrow. I plan to Cover the windows this weekend in an effort to dry the house in and begin cleaning and interior items.

Daily log

Due to high winds the framers will not be setting panels today. I have Updated the budget to reflect all paid Forest City invoices. I have also included links to the actual invoices on the Transactions page of the budget. You can find that at the bottom of the budget pdf. on your client login page. Simply click the link for the given invoice and you will be taken to the invoice pdf. and the receipts/invoices from the subs that make up that invoice.

Screen Shot 2019-01-23 at 12.41.14 PM.png